Course Update

Irrigation Irrigation works has continued well this week with all the 90mm mains pipe installed. The spoil on top of the trenches will be cleared and areas made good.  Work will now turn to mole ploughing the smaller 63mm pipes which will connect to the greens, tees and approach valve boxes.  Mole ploughing is achieved by pulling the pipe...
Continue reading
107 Hits
0 Comments

Irrigation Update

The irrigation project is progressing very well with over 1500 metres of mains pipework installed already. The 90mm pipe that members can see laying around the course will be trenched into the ground, this process does create more spoil but is a much quicker process. Later in the installation a smaller 63mm pipe will be mole ploughed which should m...
Continue reading
117 Hits
0 Comments

Irrigation

As reported last week the new irrigation ring main was marked out on Tuesday, including the location of the valve boxes. Victor Jamieson (designer) and Ashley Proctor (contractor) were both present to plot a route around the course avoiding major obstacles such as large tree roots and major services. Phase one will be the mole ploughing of the ring...
Continue reading
139 Hits
0 Comments

Course News

Levelling of the 1 st medal tee is now complete taking just over one day to complete. The tee will now be regularly top dressed and watered to help the turf establish so we can get it back into play as soon as possible. ​ Removing the turf  Once levelled the turf is laid Job completed This time of year disease is rife due to drop in night time...
Continue reading